Zhoug Guo Jia at Al Warsan First

Construction progress

Zhoug Guo Jia at Al Warsan First construction updates

International City Dubai · Tianfa Real Estate Developments L.L.C

CompletedLast site inspection February 11, 2020 · 7 years ago
100%complete

DLD first inspected the site on Feb 26, 2019 at 55.1% complete, and recorded it as finished after 2 inspections, the last on Feb 11, 2020.

First inspection · 55.1%Latest · 100%
Construction started
November 13, 2017
Completion date registered with DLD
February 11, 2020
Site inspections
2
Units
110
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2138

Latest site photos

February 11, 2020

Progress over time

Progress over time
0%25%50%75%100%2020

Inspection history

  1. February 11, 2020

    11 months after the previous inspection

    +44.9%100%
  2. February 26, 2019

    First inspection

    55.1%

Thinking about Zhoug Guo Jia at Al Warsan First?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2138), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.