Construction progress
International City Dubai · Tianfa Real Estate Developments L.L.C
DLD first inspected the site on Feb 26, 2019 at 55.1% complete, and recorded it as finished after 2 inspections, the last on Feb 11, 2020.
February 11, 2020
11 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2138), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.