Zenith Residences at Dubai International City

Construction progress

Zenith Residences at Dubai International City construction updates

International City Dubai · Art Of Amber Real Estate Development L.L.C

Under constructionLast site inspection October 7, 2026 · 31 days ago
24.1%complete

When DLD first inspected the site on May 20, 2025, it was 3% complete. After 3 inspections it now stands at 24.1%.

That is about 1.3% more of the building completed each month on average.

First inspection · 3%Latest · 24.1%
Construction started
March 1, 2025
Completion date registered with DLD
March 1, 2028
Site inspections
3
Units
267
Escrow bank
Mashreq Bank Psc
DLD project no.
3708

Latest site photos

October 7, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 7, 2026

    6 months after the previous inspection

    +12.9%24.1%
  2. March 27, 2026

    10 months after the previous inspection

    +8.2%11.2%
  3. May 20, 2025

    First inspection

    3%

Thinking about Zenith Residences at Dubai International City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3708), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.