Wynwood at Dubai Islands – Imtiaz Development

Construction progress

Wynwood at Dubai Islands – Imtiaz Development construction updates

Dubai Islands · Imtiaz Gi Real Estate Development L.L.C

Under constructionLast site inspection October 6, 2026 · 32 days ago
26.3%complete

When DLD first inspected the site on May 20, 2025, it was 0% complete. After 6 inspections it now stands at 26.3%.

That is about 1.6% more of the building completed each month on average.

First inspection · 0%Latest · 26.3%
Construction started
June 15, 2025
Completion date registered with DLD
September 30, 2027
Site inspections
6
Units
146
Escrow bank
Ajman Bank /P.J.S.C
DLD project no.
3784

Latest site photos

October 6, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 6, 2026

    3 months after the previous inspection

    +10.3%26.3%
  2. July 9, 2026

    3 months after the previous inspection

    +7.6%16%
  3. April 3, 2026

    3 months after the previous inspection

    +3.1%8.4%
  4. December 24, 2025

    3 months after the previous inspection

    +4.6%5.4%
  5. September 9, 2025

    4 months after the previous inspection

    +0.7%0.7%
  6. May 20, 2025

    First inspection

    0%

Thinking about Wynwood at Dubai Islands – Imtiaz Development?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3784), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.