Weybridge Gardens 3 at Dubailand

Construction progress

Weybridge Gardens 3 at Dubailand construction updates

Dubailand · Leos Development L.L.C

Under constructionLast site inspection August 5, 2026 · 3 months ago
23.9%complete

When DLD first inspected the site on Jul 2, 2024, it was 0% complete. After 5 inspections it now stands at 23.9%.

That is about 1% more of the building completed each month on average.

First inspection · 0%Latest · 23.9%
Construction started
December 20, 2024
Completion date registered with DLD
August 20, 2026
Site inspections
5
Units
208
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
3164

Latest site photos

August 5, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 5, 2026

    2 months after the previous inspection

    +5.2%23.9%
  2. June 1, 2026

    2 months after the previous inspection

    +3.2%18.7%
  3. March 31, 2026

    4 months after the previous inspection

    +9.6%15.5%
  4. November 18, 2025

    17 months after the previous inspection

    +5.9%5.9%
  5. July 2, 2024

    First inspection

    0%

Thinking about Weybridge Gardens 3 at Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3164), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.