Westwood Grande at JVC, Dubai

Construction progress

Westwood Grande at JVC, Dubai construction updates

JVC · Imtiaz Real Estate Investment & Development L.L.C

CompletedLast site inspection October 20, 2024 · 2 years ago
100%complete

DLD first inspected the site on Nov 29, 2022 at 0% complete, and recorded it as finished after 6 inspections, the last on Oct 20, 2024.

First inspection · 0%Latest · 100%
Construction started
November 1, 2022
Completion date registered with DLD
October 31, 2024
Site inspections
6
Units
157
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2520

Latest site photos

October 20, 2024

Progress over time

Progress over time
0%25%50%75%100%20232024

Inspection history

  1. October 20, 2024

    5 months after the previous inspection

    +41.9%100%
  2. May 13, 2024

    6 months after the previous inspection

    +38%58.1%
  3. November 2, 2023

    4 months after the previous inspection

    +12.6%20.1%
  4. June 22, 2023

    5 months after the previous inspection

    +7.1%7.5%
  5. January 19, 2023

    2 months after the previous inspection

    +0.4%0.4%
  6. November 29, 2022

    First inspection

    0%

Thinking about Westwood Grande at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2520), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.