Westwood Grande 2 at JVC, Dubai

Construction progress

Westwood Grande 2 at JVC, Dubai construction updates

JVC · Imtiaz Real Estate Investment & Development L.L.C

CompletedLast site inspection May 31, 2025 · 17 months ago
100%complete

DLD first inspected the site on Apr 25, 2023 at 0.1% complete, and recorded it as finished after 6 inspections, the last on May 31, 2025.

First inspection · 0.1%Latest · 100%
Construction started
April 15, 2023
Site inspections
6
Units
153
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2645

Latest site photos

May 31, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. May 31, 2025

    2 months after the previous inspection

    +9.5%100%
  2. April 15, 2025

    4 months after the previous inspection

    +33%90.5%
  3. December 17, 2024

    9 months after the previous inspection

    +45.9%57.5%
  4. March 14, 2024

    6 months after the previous inspection

    +9.8%11.6%
  5. September 18, 2023

    5 months after the previous inspection

    +1.7%1.8%
  6. April 25, 2023

    First inspection

    0.1%

Thinking about Westwood Grande 2 at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2645), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.