Construction progress
Dubailand · Danube Properties Development L.L.C
DLD first inspected the site on Apr 21, 2020 at 0.3% complete, and recorded it as finished after 12 inspections, the last on Jul 10, 2023.
July 10, 2023
6 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
5 months after the previous inspection
3 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2175), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.