Wavez Residence by Danube

Construction progress

Wavez Residence by Danube construction updates

Dubailand · Danube Properties Development L.L.C

CompletedLast site inspection July 10, 2023 · 3 years ago
100%complete

DLD first inspected the site on Apr 21, 2020 at 0.3% complete, and recorded it as finished after 12 inspections, the last on Jul 10, 2023.

First inspection · 0.3%Latest · 100%
Construction started
September 30, 2019
Completion date registered with DLD
September 30, 2022
Site inspections
12
Units
434
Escrow bank
Mashreq Bank Psc
DLD project no.
2175

Latest site photos

July 10, 2023

Progress over time

Progress over time
0%25%50%75%100%202120222023

Inspection history

  1. July 10, 2023

    6 months after the previous inspection

    +12.8%100%
  2. January 16, 2023

    3 months after the previous inspection

    +14.2%87.2%
  3. October 4, 2022

    3 months after the previous inspection

    +12.9%73%
  4. July 14, 2022

    3 months after the previous inspection

    +9.8%60%
  5. April 5, 2022

    3 months after the previous inspection

    +6.9%50.3%
  6. December 30, 2021

    3 months after the previous inspection

    +6.3%43.4%
  7. September 28, 2021

    3 months after the previous inspection

    +8.9%37%
  8. June 30, 2021

    3 months after the previous inspection

    +8.1%28.1%
  9. March 30, 2021

    4 months after the previous inspection

    +9%20%
  10. December 7, 2020

    5 months after the previous inspection

    +8.5%11%
  11. July 23, 2020

    3 months after the previous inspection

    +2.2%2.5%
  12. April 21, 2020

    First inspection

    0.3%

Thinking about Wavez Residence by Danube?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2175), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.