Waref Residences at JVC, Dubai

Construction progress

Waref Residences at JVC, Dubai construction updates

JVC · Sido Development L.L.C

Under constructionLast site inspection April 28, 2026 · 6 months ago
81.1%complete

When DLD first inspected the site on Jul 3, 2024, it was 12.4% complete. After 7 inspections it now stands at 81.1%.

That is about 3.1% more of the building completed each month on average.

First inspection · 12.4%Latest · 81.1%
Construction started
February 29, 2024
Completion date registered with DLD
May 1, 2026
Site inspections
7
Units
228
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3036

Latest site photos

April 28, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. April 28, 2026

    2 months after the previous inspection

    +10.3%81.1%
  2. February 11, 2026

    0 days after the previous inspection

    70.8%
  3. February 11, 2026

    2 months after the previous inspection

    +12.5%70.8%
  4. November 27, 2025

    4 months after the previous inspection

    +13.9%58.3%
  5. July 22, 2025

    3 months after the previous inspection

    +14.7%44.4%
  6. April 18, 2025

    9 months after the previous inspection

    +17.3%29.7%
  7. July 3, 2024

    First inspection

    12.4%

Thinking about Waref Residences at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3036), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.