VYB at Business Bay

Construction progress

VYB at Business Bay construction updates

Business Bay · Ginco Properties L.L.C

CompletedLast site inspection June 16, 2026 · 5 months ago
100%complete

DLD first inspected the site on Jul 26, 2023 at 0% complete, and recorded it as finished after 8 inspections, the last on Jun 16, 2026.

First inspection · 0%Latest · 100%
Construction started
August 1, 2023
Completion date registered with DLD
February 28, 2026
Site inspections
8
Units
181
Escrow bank
Emirates Islamic Bank P.J.S.C.
DLD project no.
2727

Latest site photos

June 16, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. June 16, 2026

    0 days after the previous inspection

    100%
  2. June 16, 2026

    4 months after the previous inspection

    +1.9%100%
  3. February 9, 2026

    4 months after the previous inspection

    +30.2%98.1%
  4. October 3, 2025

    6 months after the previous inspection

    +19.9%67.9%
  5. April 18, 2025

    4 months after the previous inspection

    +20%48.1%
  6. December 10, 2024

    6 months after the previous inspection

    +14.5%28.1%
  7. May 28, 2024

    10 months after the previous inspection

    +13.6%13.6%
  8. July 26, 2023

    First inspection

    0%

Thinking about VYB at Business Bay?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2727), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.