VUE by Crystal Bay at JVC, Dubai

Construction progress

VUE by Crystal Bay at JVC, Dubai construction updates

JVC · Crystal Bay Development L.L.C

Under constructionLast site inspection August 27, 2026 · 2 months ago
68.2%complete

When DLD first inspected the site on May 15, 2024, it was 0% complete. After 6 inspections it now stands at 68.2%.

That is about 2.5% more of the building completed each month on average.

First inspection · 0%Latest · 68.2%
Construction started
April 1, 2024
Completion date registered with DLD
October 1, 2026
Site inspections
6
Units
176
Escrow bank
Mashreq Bank Psc
DLD project no.
3090

Latest site photos

August 27, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 27, 2026

    3 months after the previous inspection

    +14%68.2%
  2. June 9, 2026

    4 months after the previous inspection

    +18.5%54.2%
  3. January 28, 2026

    4 months after the previous inspection

    +14.4%35.7%
  4. September 15, 2025

    4 months after the previous inspection

    +6.7%21.3%
  5. May 12, 2025

    12 months after the previous inspection

    +14.7%14.7%
  6. May 15, 2024

    First inspection

    0%

Thinking about VUE by Crystal Bay at JVC, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3090), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.