Volta Tower by Damac

Construction progress

Volta Tower by Damac construction updates

Downtown Dubai · Damac C S L Investment L.L.C

Under constructionLast site inspection August 18, 2026 · 3 months ago
29.3%complete

When DLD first inspected the site on Sep 14, 2023, it was 0% complete. After 8 inspections it now stands at 29.3%.

That is about 0.8% more of the building completed each month on average.

First inspection · 0%Latest · 29.3%
Construction started
December 13, 2023
Completion date registered with DLD
December 31, 2027
Site inspections
8
Units
417
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2782

Latest site photos

August 18, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 18, 2026

    4 months after the previous inspection

    +8.5%29.3%
  2. April 11, 2026

    4 months after the previous inspection

    +5.9%20.8%
  3. December 11, 2025

    4 months after the previous inspection

    +2%14.9%
  4. August 4, 2025

    4 months after the previous inspection

    +5.3%12.8%
  5. April 10, 2025

    5 months after the previous inspection

    +2.3%7.6%
  6. November 20, 2024

    5 months after the previous inspection

    +4.1%5.2%
  7. July 5, 2024

    10 months after the previous inspection

    +1.1%1.1%
  8. September 14, 2023

    First inspection

    0%

Thinking about Volta Tower by Damac?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2782), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.