Volga Tower by Tiger Group

Construction progress

Volga Tower by Tiger Group construction updates

JVT · Tiger Properties

Under constructionLast site inspection October 5, 2026 · 33 days ago
51.1%complete

When DLD first inspected the site on Jul 12, 2023, it was 0% complete. After 9 inspections it now stands at 51.1%.

That is about 1.3% more of the building completed each month on average.

First inspection · 0%Latest · 51.1%
Construction started
September 1, 2023
Site inspections
9
Units
391
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2715

Latest site photos

October 5, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 5, 2026

    0 days after the previous inspection

    51.1%
  2. October 5, 2026

    3 months after the previous inspection

    +13.2%51.1%
  3. June 25, 2026

    3 months after the previous inspection

    +3.9%37.9%
  4. April 6, 2026

    3 months after the previous inspection

    +8%34.1%
  5. December 29, 2025

    5 months after the previous inspection

    +7.8%26.1%
  6. July 24, 2025

    5 months after the previous inspection

    +6.6%18.3%
  7. February 20, 2025

    19 months after the previous inspection

    +11.7%11.7%
  8. July 12, 2023

    0 days after the previous inspection

    0%
  9. July 12, 2023

    First inspection

    0%

Thinking about Volga Tower by Tiger Group?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2715), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.