VISTARA House at Al Furjan Dubai

Construction progress

VISTARA House at Al Furjan Dubai construction updates

Al Furjan · Object One Real Estate Development L.L.C

Under constructionLast site inspection July 23, 2026 · 4 months ago
7%complete

When DLD first inspected the site on Dec 11, 2024, it was 0% complete. After 5 inspections it now stands at 7%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 7%
Construction started
December 20, 2024
Completion date registered with DLD
March 30, 2027
Site inspections
5
Units
141
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
3448

Latest site photos

July 23, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 23, 2026

    3 months after the previous inspection

    +0.9%7%
  2. April 20, 2026

    6 months after the previous inspection

    +1%6.1%
  3. November 3, 2025

    3 months after the previous inspection

    +3.3%5.1%
  4. July 28, 2025

    8 months after the previous inspection

    +1.8%1.8%
  5. December 11, 2024

    First inspection

    0%

Thinking about VISTARA House at Al Furjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3448), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.