Vista by Vision

Construction progress

Vista by Vision construction updates

Dubai Production City (IMPZ) · Clear Vision Real Estate Development L.L.C

Under constructionLast site inspection October 12, 2026 · 26 days ago
12.2%complete

When DLD first inspected the site on Oct 28, 2025, it was 0% complete. After 3 inspections it now stands at 12.2%.

That is about 1.1% more of the building completed each month on average.

First inspection · 0%Latest · 12.2%
Construction started
January 1, 2026
Completion date registered with DLD
September 1, 2027
Site inspections
3
Units
328
Escrow bank
The National Bank Of Fujairah P S C
DLD project no.
4175

Latest site photos

October 12, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 12, 2026

    5 months after the previous inspection

    +8.8%12.2%
  2. May 14, 2026

    7 months after the previous inspection

    +3.4%3.4%
  3. October 28, 2025

    First inspection

    0%

Thinking about Vista by Vision?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4175), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat