Vincitore Dolce Vita Dubai

Construction progress

Vincitore Dolce Vita Dubai construction updates

Arjan Dubai · Vincitore Premium Real Estate Development L.L.C

Under constructionLast site inspection October 23, 2026 · 15 days ago
40%complete

When DLD first inspected the site on Jun 12, 2023, it was 0% complete. After 7 inspections it now stands at 40%.

That is about 1% more of the building completed each month on average.

First inspection · 0%Latest · 40%
Construction started
June 30, 2023
Site inspections
7
Units
715
Buildings
2
Escrow bank
Mashreq Bank Psc
DLD project no.
2669

Latest site photos

October 23, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. October 23, 2026

    6 months after the previous inspection

    +18%40%
  2. April 22, 2026

    4 months after the previous inspection

    +5.4%22%
  3. December 12, 2025

    5 months after the previous inspection

    +9.6%16.7%
  4. July 21, 2025

    7 months after the previous inspection

    +1.2%7.1%
  5. December 16, 2024

    6 months after the previous inspection

    +5.8%5.8%
  6. June 26, 2024

    12 months after the previous inspection

    +0%0%
  7. June 12, 2023

    First inspection

    0%

Thinking about Vincitore Dolce Vita Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2669), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.