Vincitore Benessere at Arjan Dubai

Construction progress

Vincitore Benessere at Arjan Dubai construction updates

Dubailand · Vincitore Real Estate Development L.L.C

CompletedLast site inspection January 8, 2025 · 2 years ago
100%complete

DLD first inspected the site on Nov 13, 2019 at 0.4% complete, and recorded it as finished after 8 inspections, the last on Jan 8, 2025.

First inspection · 0.4%Latest · 100%
Construction started
June 1, 2019
Completion date registered with DLD
January 9, 2023
Site inspections
8
Units
419
Buildings
2
Escrow bank
Mashreq Bank Psc
DLD project no.
2149

Latest site photos

January 8, 2025

Progress over time

Progress over time
0%25%50%75%100%202020212022202320242025

Inspection history

  1. January 8, 2025

    7 months after the previous inspection

    +9.3%100%
  2. June 6, 2024

    9 months after the previous inspection

    +25.5%90.7%
  3. September 7, 2023

    15 months after the previous inspection

    +15.1%65.2%
  4. June 13, 2022

    5 months after the previous inspection

    +22.2%50.1%
  5. January 19, 2022

    5 months after the previous inspection

    +16.8%27.9%
  6. August 30, 2021

    7 months after the previous inspection

    +10%11.1%
  7. February 2, 2021

    15 months after the previous inspection

    +0.7%1.1%
  8. November 13, 2019

    First inspection

    0.4%

Thinking about Vincitore Benessere at Arjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2149), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.