Verde by Sobha at JLT

Construction progress

Verde by Sobha at JLT construction updates

JLT · Sobha L.L.C

Under constructionLast site inspection August 24, 2026 · 2 months ago
85%complete

When DLD first inspected the site on Feb 16, 2023, it was 0% complete. After 9 inspections it now stands at 85%.

That is about 2% more of the building completed each month on average.

First inspection · 0%Latest · 85%
Construction started
April 1, 2023
Completion date registered with DLD
June 30, 2027
Site inspections
9
Units
610
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2583

Latest site photos

August 24, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 24, 2026

    3 months after the previous inspection

    +9.4%85%
  2. May 22, 2026

    3 months after the previous inspection

    +13.9%75.6%
  3. February 23, 2026

    4 months after the previous inspection

    +16.7%61.7%
  4. November 5, 2025

    7 months after the previous inspection

    +18.3%45%
  5. April 17, 2025

    4 months after the previous inspection

    +7.8%26.7%
  6. December 23, 2024

    9 months after the previous inspection

    +9.5%18.9%
  7. March 15, 2024

    5 months after the previous inspection

    +5.1%9.4%
  8. October 6, 2023

    8 months after the previous inspection

    +4.4%4.4%
  9. February 16, 2023

    First inspection

    0%

Thinking about Verde by Sobha at JLT?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2583), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.