Veona at DLRC

Construction progress

Veona at DLRC construction updates

Dubai Land Residence Complex (DLRC) · Gutti Real Estate Development L.L.C

Under constructionLast site inspection October 14, 2026 · 24 days ago
21.7%complete

When DLD first inspected the site on Aug 11, 2025, it was 0% complete. After 4 inspections it now stands at 21.7%.

That is about 1.5% more of the building completed each month on average.

First inspection · 0%Latest · 21.7%
Construction started
November 1, 2025
Completion date registered with DLD
December 31, 2027
Site inspections
4
Units
90
Escrow bank
Mashreq Bank Psc
DLD project no.
4001

Latest site photos

October 14, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. October 14, 2026

    4 months after the previous inspection

    +10.6%21.7%
  2. June 18, 2026

    4 months after the previous inspection

    +8.9%11.1%
  3. February 9, 2026

    6 months after the previous inspection

    +2.1%2.1%
  4. August 11, 2025

    First inspection

    0%

Thinking about Veona at DLRC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4001), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.