VEGA Residences at Dubai Sports City

Construction progress

VEGA Residences at Dubai Sports City construction updates

Sports City Dubai · Acube Real Estate Development L L C

Under constructionLast site inspection August 19, 2026 · 3 months ago
20.3%complete

When DLD first inspected the site on Nov 21, 2024, it was 0% complete. After 5 inspections it now stands at 20.3%.

That is about 1% more of the building completed each month on average.

First inspection · 0%Latest · 20.3%
Construction started
January 15, 2025
Completion date registered with DLD
May 15, 2027
Site inspections
5
Units
129
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3414

Latest site photos

August 19, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 19, 2026

    4 months after the previous inspection

    +5.2%20.3%
  2. April 27, 2026

    5 months after the previous inspection

    +6.9%15.1%
  3. December 9, 2025

    5 months after the previous inspection

    +5.4%8.2%
  4. July 1, 2025

    7 months after the previous inspection

    +2.8%2.8%
  5. November 21, 2024

    First inspection

    0%

Thinking about VEGA Residences at Dubai Sports City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3414), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.