Valoria The Oasis

Construction progress

Valoria The Oasis construction updates

The Oasis by Emaar · Emaar Development P.J.S.C.

Under constructionLast site inspection July 7, 2026 · 4 months ago
1.1%complete

When DLD first inspected the site on Dec 10, 2025, it was 0% complete. After 2 inspections it now stands at 1.1%.

That is about 0.2% more of the building completed each month on average.

First inspection · 0%Latest · 1.1%
Construction started
January 22, 2026
Completion date registered with DLD
December 31, 2029
Site inspections
2
Units
257
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
4277

Latest site photos

July 7, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 7, 2026

    7 months after the previous inspection

    +1.1%1.1%
  2. December 10, 2025

    First inspection

    0%

Thinking about Valoria The Oasis?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4277), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat