VAL by Kasco Properties at Al Jaddaf

Construction progress

VAL by Kasco Properties at Al Jaddaf construction updates

Al Jaddaf · Kasco Real Estate Development L.L.C

Under constructionLast site inspection August 19, 2026 · 3 months ago
72.5%complete

When DLD first inspected the site on Jun 19, 2024, it was 0% complete. After 7 inspections it now stands at 72.5%.

That is about 2.8% more of the building completed each month on average.

First inspection · 0%Latest · 72.5%
Construction started
August 1, 2024
Completion date registered with DLD
December 30, 2026
Site inspections
7
Units
134
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3142

Latest site photos

August 19, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 19, 2026

    3 months after the previous inspection

    +15.2%72.5%
  2. May 6, 2026

    3 months after the previous inspection

    +16%57.4%
  3. January 30, 2026

    3 months after the previous inspection

    +15.2%41.4%
  4. October 31, 2025

    5 months after the previous inspection

    +13.3%26.3%
  5. June 2, 2025

    4 months after the previous inspection

    +5.8%13%
  6. February 14, 2025

    8 months after the previous inspection

    +7.2%7.2%
  7. June 19, 2024

    First inspection

    0%

Thinking about VAL by Kasco Properties at Al Jaddaf?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3142), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.