V1TER Residence at JVC Dubai

Construction progress

V1TER Residence at JVC Dubai construction updates

JVC · Object One Real Estate Development L.L.C

CompletedLast site inspection July 2, 2026 · 4 months ago
100%complete

DLD first inspected the site on Sep 8, 2023 at 0% complete, and recorded it as finished after 9 inspections, the last on Jul 2, 2026.

First inspection · 0%Latest · 100%
Construction started
August 15, 2023
Completion date registered with DLD
September 15, 2025
Site inspections
9
Units
175
Escrow bank
Abu Dhabi Islamic Bank
DLD project no.
2710

Latest site photos

July 2, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. July 2, 2026

    2 months after the previous inspection

    +5%100%
  2. April 17, 2026

    5 months after the previous inspection

    +6.8%95%
  3. November 27, 2025

    6 months after the previous inspection

    +28%88.2%
  4. June 9, 2025

    5 months after the previous inspection

    +30.1%60.2%
  5. January 9, 2025

    3 months after the previous inspection

    +10%30.1%
  6. October 10, 2024

    4 months after the previous inspection

    +11.8%20.1%
  7. June 3, 2024

    3 months after the previous inspection

    +3.3%8.3%
  8. February 26, 2024

    6 months after the previous inspection

    +5%5%
  9. September 8, 2023

    First inspection

    0%

Thinking about V1TER Residence at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2710), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.