Binghatti Twilight at Al Jaddaf, Dubai

Construction progress

Binghatti Twilight at Al Jaddaf, Dubai construction updates

Al Jaddaf · Binghatti Developers Fze

Under constructionLast site inspection September 14, 2026 · 2 months ago
55.4%complete

When DLD first inspected the site on Nov 14, 2024, it was 0% complete. After 3 inspections it now stands at 55.4%.

That is about 2.5% more of the building completed each month on average.

First inspection · 0%Latest · 55.4%
Construction started
April 1, 2025
Completion date registered with DLD
April 30, 2026
Site inspections
3
Units
277
Escrow bank
Sharjah Islamic Bank
DLD project no.
3397

Latest site photos

September 14, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 14, 2026

    5 months after the previous inspection

    +23.4%55.4%
  2. April 30, 2026

    17 months after the previous inspection

    +32%32%
  3. November 14, 2024

    First inspection

    0%

Thinking about Binghatti Twilight at Al Jaddaf, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3397), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.