Tria by Deyaar at DSO

Construction progress

Tria by Deyaar at DSO construction updates

Dubai Silicon Oasis · Deyaar Bay Real Estate Development L.L.C

Under constructionLast site inspection August 25, 2026 · 2 months ago
94.1%complete

When DLD first inspected the site on Feb 7, 2023, it was 0% complete. After 10 inspections it now stands at 94.1%.

That is about 2.2% more of the building completed each month on average.

First inspection · 0%Latest · 94.1%
Construction started
August 1, 2022
Completion date registered with DLD
June 30, 2025
Site inspections
10
Units
717
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2403

Latest site photos

August 25, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 25, 2026

    22 days after the previous inspection

    +0.7%94.1%
  2. August 3, 2026

    3 months after the previous inspection

    +6.2%93.4%
  3. April 24, 2026

    3 months after the previous inspection

    +7%87.1%
  4. January 13, 2026

    6 months after the previous inspection

    +27.5%80.1%
  5. July 10, 2025

    5 months after the previous inspection

    +8.4%52.6%
  6. February 7, 2025

    7 months after the previous inspection

    +15.6%44.2%
  7. July 22, 2024

    4 months after the previous inspection

    +15.4%28.6%
  8. March 13, 2024

    7 months after the previous inspection

    +8.6%13.2%
  9. August 2, 2023

    6 months after the previous inspection

    +4.6%4.7%
  10. February 7, 2023

    First inspection

    0%

Thinking about Tria by Deyaar at DSO?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2403), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat