Treppan Tower at Jumeirah Village Triangle

Construction progress

Treppan Tower at Jumeirah Village Triangle construction updates

JVT · Fakhruddin Properties Development L.L.C

Under constructionLast site inspection August 7, 2026 · 3 months ago
11.9%complete

When DLD first inspected the site on Oct 24, 2024, it was 0% complete. After 3 inspections it now stands at 11.9%.

That is about 0.6% more of the building completed each month on average.

First inspection · 0%Latest · 11.9%
Construction started
January 1, 2025
Completion date registered with DLD
April 1, 2027
Site inspections
3
Units
263
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
3348

Latest site photos

August 7, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 7, 2026

    4 months after the previous inspection

    +7.2%11.9%
  2. April 15, 2026

    18 months after the previous inspection

    +4.7%4.7%
  3. October 24, 2024

    First inspection

    0%

Thinking about Treppan Tower at Jumeirah Village Triangle?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3348), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.