Tonino Lamborghini Residences at Nad Al Sheba

Construction progress

Tonino Lamborghini Residences at Nad Al Sheba construction updates

Meydan, Nad Al Sheba 1 · Gulf Land Property Developers L.L.C

Under constructionLast site inspection September 21, 2026 · 2 months ago
60%complete

When DLD first inspected the site on Mar 27, 2018, it was 1.2% complete. After 13 inspections it now stands at 60%.

That is about 0.6% more of the building completed each month on average.

First inspection · 1.2%Latest · 60%
Construction started
October 1, 2017
Completion date registered with DLD
December 31, 2026
Site inspections
13
Units
553
Buildings
4
Escrow bank
Commercial Bank International P.J.S.C
DLD project no.
1941

Latest site photos

September 21, 2026

Progress over time

Progress over time
0%25%50%75%100%20192020202120222023202420252026

Inspection history

  1. September 21, 2026

    11 days after the previous inspection

    +6.1%60%
  2. September 10, 2026

    6 months after the previous inspection

    +2%53.9%
  3. March 24, 2026

    5 months after the previous inspection

    +1.3%51.9%
  4. October 30, 2025

    4 months after the previous inspection

    +0.4%50.5%
  5. June 18, 2025

    5 months after the previous inspection

    +9.8%50.1%
  6. January 30, 2025

    37 days after the previous inspection

    +6.1%40.3%
  7. December 24, 2024

    7 months after the previous inspection

    +6.9%34.1%
  8. June 7, 2024

    46 months after the previous inspection

    +1%27.2%
  9. August 17, 2020

    16 months after the previous inspection

    +0.7%26.2%
  10. April 17, 2019

    3 months after the previous inspection

    +5.4%25.6%
  11. January 30, 2019

    7 months after the previous inspection

    +7.3%20.1%
  12. July 12, 2018

    4 months after the previous inspection

    +11.6%12.8%
  13. March 27, 2018

    First inspection

    1.2%

Thinking about Tonino Lamborghini Residences at Nad Al Sheba?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 1941), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.