Construction progress
Meydan, Nad Al Sheba 1 · Gulf Land Property Developers L.L.C
When DLD first inspected the site on Mar 27, 2018, it was 1.2% complete. After 13 inspections it now stands at 60%.
That is about 0.6% more of the building completed each month on average.
September 21, 2026
11 days after the previous inspection
6 months after the previous inspection
5 months after the previous inspection
4 months after the previous inspection
5 months after the previous inspection
37 days after the previous inspection
7 months after the previous inspection
46 months after the previous inspection
16 months after the previous inspection
3 months after the previous inspection
7 months after the previous inspection
4 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 1941), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.