Timez by Danube at Dubai Silicon Oasis

Construction progress

Timez by Danube at Dubai Silicon Oasis construction updates

Dubai Silicon Oasis · Danube Properties Development L.L.C

Under constructionLast site inspection September 9, 2026 · 2 months ago
21.5%complete

When DLD first inspected the site on Feb 11, 2025, it was 0% complete. After 7 inspections it now stands at 21.5%.

That is about 1.1% more of the building completed each month on average.

First inspection · 0%Latest · 21.5%
Construction started
April 1, 2025
Completion date registered with DLD
July 31, 2028
Site inspections
7
Units
1,191
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3559

Latest site photos

September 9, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. September 9, 2026

    4 months after the previous inspection

    +4.4%21.5%
  2. May 12, 2026

    2 months after the previous inspection

    +7.3%17.1%
  3. March 17, 2026

    2 months after the previous inspection

    +2.5%9.7%
  4. January 13, 2026

    3 months after the previous inspection

    +3%7.2%
  5. October 28, 2025

    4 months after the previous inspection

    +3%4.2%
  6. July 1, 2025

    5 months after the previous inspection

    +1.2%1.2%
  7. February 11, 2025

    First inspection

    0%

Thinking about Timez by Danube at Dubai Silicon Oasis?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3559), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.