Tiger Sky Tower at Business Bay Dubai

Construction progress

Tiger Sky Tower at Business Bay Dubai construction updates

Business Bay · Tiger Properties

Under constructionLast site inspection September 10, 2026 · 2 months ago
10.2%complete

When DLD first inspected the site on May 14, 2024, it was 2.8% complete. After 8 inspections it now stands at 10.2%.

That is about 0.3% more of the building completed each month on average.

First inspection · 2.8%Latest · 10.2%
Construction started
May 1, 2024
Site inspections
8
Units
849
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2579

Latest site photos

September 10, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 10, 2026

    4 months after the previous inspection

    +0.9%10.2%
  2. May 21, 2026

    5 months after the previous inspection

    +2%9.3%
  3. December 31, 2025

    0 days after the previous inspection

    +0.2%7.3%
  4. December 31, 2025

    6 months after the previous inspection

    +0.3%7.1%
  5. July 4, 2025

    5 months after the previous inspection

    +1%6.8%
  6. January 21, 2025

    8 months after the previous inspection

    +3.1%5.8%
  7. May 14, 2024

    0 days after the previous inspection

    2.8%
  8. May 14, 2024

    First inspection

    2.8%

Thinking about Tiger Sky Tower at Business Bay Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2579), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.