The Residence Burj Khalifa by Emaar

Construction progress

The Residence Burj Khalifa by Emaar construction updates

Downtown Dubai · Emaar Properties (P.J.S.C)

CompletedLast site inspection September 21, 2026 · 2 months ago
100%complete

DLD first inspected the site on Aug 23, 2022 at 63.2% complete, and recorded it as finished after 9 inspections, the last on Sep 21, 2026.

First inspection · 63.2%Latest · 100%
Construction started
March 21, 2023
Completion date registered with DLD
December 31, 2024
Site inspections
9
Units
35
Buildings
8
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
2443

Latest site photos

September 21, 2026

Progress over time

Progress over time
0%25%50%75%100%2023202420252026

Inspection history

  1. September 21, 2026

    5 months after the previous inspection

    +7.3%100%
  2. May 7, 2026

    5 months after the previous inspection

    +6.6%92.7%
  3. December 4, 2025

    4 months after the previous inspection

    +5.8%86.1%
  4. July 28, 2025

    4 months after the previous inspection

    +10.2%80.4%
  5. March 27, 2025

    5 months after the previous inspection

    +0.1%70.2%
  6. October 15, 2024

    5 months after the previous inspection

    +6%70.1%
  7. May 7, 2024

    6 months after the previous inspection

    64.1%
  8. November 15, 2023

    15 months after the previous inspection

    +0.9%64.1%
  9. August 23, 2022

    First inspection

    63.2%

Thinking about The Residence Burj Khalifa by Emaar?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2443), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.