Construction progress

The Portman at JVC construction updates

JVC · Ellington Properties Development L.L.C

Under constructionLast site inspection August 7, 2026 · 3 months ago
78.7%complete

When DLD first inspected the site on Dec 22, 2022, it was 0% complete. After 9 inspections it now stands at 78.7%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 78.7%
Construction started
December 12, 2022
Completion date registered with DLD
September 30, 2025
Site inspections
9
Units
167
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2537

Latest site photos

August 7, 2026

Progress over time

Progress over time
0%25%50%75%100%2023202420252026

Inspection history

  1. August 7, 2026

    4 months after the previous inspection

    +22%78.7%
  2. April 20, 2026

    5 months after the previous inspection

    +6.1%56.7%
  3. November 24, 2025

    6 months after the previous inspection

    +14%50.6%
  4. June 3, 2025

    4 months after the previous inspection

    +21.7%36.5%
  5. January 29, 2025

    7 months after the previous inspection

    +9.6%14.8%
  6. June 26, 2024

    8 months after the previous inspection

    +1.1%5.3%
  7. October 30, 2023

    6 months after the previous inspection

    +4.1%4.2%
  8. May 9, 2023

    5 months after the previous inspection

    +0%0%
  9. December 22, 2022

    First inspection

    0%

Thinking about The Portman at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2537), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.