The Pier Residence at Dubai Maritime City

Construction progress

The Pier Residence at Dubai Maritime City construction updates

Dubai Maritime City · Continental Investments Lmd L.L.C

Under constructionLast site inspection October 20, 2026 · 18 days ago
48.4%complete

When DLD first inspected the site on Jun 27, 2024, it was 0% complete. After 7 inspections it now stands at 48.4%.

That is about 1.7% more of the building completed each month on average.

First inspection · 0%Latest · 48.4%
Construction started
July 1, 2024
Completion date registered with DLD
December 31, 2026
Site inspections
7
Units
282
Escrow bank
The National Bank Of Fujairah P S C
DLD project no.
3110

Latest site photos

October 20, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 20, 2026

    3 months after the previous inspection

    +13.6%48.4%
  2. July 14, 2026

    3 months after the previous inspection

    +8.6%34.8%
  3. April 10, 2026

    4 months after the previous inspection

    +6.3%26.3%
  4. December 15, 2025

    4 months after the previous inspection

    +8%20%
  5. August 26, 2025

    5 months after the previous inspection

    +6.6%12%
  6. April 2, 2025

    9 months after the previous inspection

    +5.4%5.4%
  7. June 27, 2024

    First inspection

    0%

Thinking about The Pier Residence at Dubai Maritime City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3110), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.