The Highgrove by Ellington at Meydan

Construction progress

The Highgrove by Ellington at Meydan construction updates

Meydan Dubai · Ellington Properties Development L.L.C

Under constructionLast site inspection August 6, 2026 · 3 months ago
7%complete

When DLD first inspected the site on Aug 26, 2025, it was 0% complete. After 3 inspections it now stands at 7%.

That is about 0.6% more of the building completed each month on average.

First inspection · 0%Latest · 7%
Construction started
September 1, 2025
Completion date registered with DLD
December 31, 2028
Site inspections
3
Units
296
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
4037

Latest site photos

August 6, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. August 6, 2026

    4 months after the previous inspection

    +2.7%7%
  2. April 16, 2026

    8 months after the previous inspection

    +4.3%4.3%
  3. August 26, 2025

    First inspection

    0%

Thinking about The Highgrove by Ellington at Meydan?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 4037), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.