The Diplomat Residences at Town Square Dubai

Construction progress

The Diplomat Residences at Town Square Dubai construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

CompletedLast site inspection December 12, 2024 · 2 years ago
100%complete

DLD first inspected the site on Nov 29, 2022 at 0% complete, and recorded it as finished after 6 inspections, the last on Dec 12, 2024.

First inspection · 0%Latest · 100%
Construction started
March 1, 2023
Completion date registered with DLD
November 30, 2024
Site inspections
6
Units
153
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2524

Latest site photos

December 12, 2024

Progress over time

Progress over time
0%25%50%75%100%20232024

Inspection history

  1. December 12, 2024

    0 days after the previous inspection

    100%
  2. December 12, 2024

    6 months after the previous inspection

    +37.9%100%
  3. June 10, 2024

    6 months after the previous inspection

    +40.5%62.1%
  4. December 14, 2023

    4 months after the previous inspection

    +17.6%21.6%
  5. August 14, 2023

    8 months after the previous inspection

    +4%4%
  6. November 29, 2022

    First inspection

    0%

Thinking about The Diplomat Residences at Town Square Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2524), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat