The Crestmark by Ellington at Business Bay

Construction progress

The Crestmark by Ellington at Business Bay construction updates

Business Bay · Ellington Properties Development L.L.C

Under constructionLast site inspection August 7, 2026 · 3 months ago
61.2%complete

When DLD first inspected the site on Oct 25, 2023, it was 0% complete. After 7 inspections it now stands at 61.2%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 61.2%
Construction started
September 26, 2023
Site inspections
7
Units
191
Escrow bank
Commercial Bank Of Dubai(Psc)
DLD project no.
2832

Latest site photos

August 7, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. August 7, 2026

    3 months after the previous inspection

    +17.5%61.2%
  2. April 23, 2026

    4 months after the previous inspection

    +12.1%43.6%
  3. December 23, 2025

    4 months after the previous inspection

    +6.9%31.5%
  4. August 26, 2025

    5 months after the previous inspection

    +9.9%24.6%
  5. April 9, 2025

    9 months after the previous inspection

    +9.4%14.7%
  6. July 4, 2024

    8 months after the previous inspection

    +5.3%5.3%
  7. October 25, 2023

    First inspection

    0%

Thinking about The Crestmark by Ellington at Business Bay?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2832), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.