The Corner at Dubailand

Construction progress

The Corner at Dubailand construction updates

Dubailand · Arabian Gulf Properties

Under constructionLast site inspection June 1, 2026 · 5 months ago
37.7%complete

When DLD first inspected the site on Dec 10, 2024, it was 2.2% complete. After 5 inspections it now stands at 37.7%.

That is about 2% more of the building completed each month on average.

First inspection · 2.2%Latest · 37.7%
Construction started
September 1, 2024
Completion date registered with DLD
June 30, 2027
Site inspections
5
Units
126
Escrow bank
Mashreq Bank Psc
DLD project no.
2904

Latest site photos

June 1, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. June 1, 2026

    4 months after the previous inspection

    +3.9%37.7%
  2. February 6, 2026

    5 months after the previous inspection

    +8.4%33.8%
  3. September 8, 2025

    4 months after the previous inspection

    +8.1%25.4%
  4. May 20, 2025

    5 months after the previous inspection

    +15.1%17.3%
  5. December 10, 2024

    First inspection

    2.2%

Thinking about The Corner at Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2904), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.