The Central Downtown at Arjan Dubai

Construction progress

The Central Downtown at Arjan Dubai construction updates

Arjan Dubai · Aqua Properties Fz -Llc

Under constructionLast site inspection April 21, 2026 · 7 months ago
10.5%complete

When DLD first inspected the site on Nov 24, 2023, it was 0% complete. After 4 inspections it now stands at 10.5%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 10.5%
Construction started
November 1, 2023
Completion date registered with DLD
March 31, 2028
Site inspections
4
Units
1,254
Buildings
5
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2861

Latest site photos

April 21, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. April 21, 2026

    11 months after the previous inspection

    +6.3%10.5%
  2. May 22, 2025

    6 months after the previous inspection

    +3.5%4.2%
  3. November 15, 2024

    12 months after the previous inspection

    +0.7%0.7%
  4. November 24, 2023

    First inspection

    0%

Thinking about The Central Downtown at Arjan Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2861), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.