The Autograph S Series at JVC Dubai

Construction progress

The Autograph S Series at JVC Dubai construction updates

JVC · Green Properties Development Co. L.L.C

Under constructionLast site inspection April 14, 2026 · 7 months ago
18.5%complete

When DLD first inspected the site on Aug 6, 2024, it was 0% complete. After 3 inspections it now stands at 18.5%.

That is about 0.9% more of the building completed each month on average.

First inspection · 0%Latest · 18.5%
Construction started
October 30, 2024
Completion date registered with DLD
December 31, 2027
Site inspections
3
Units
253
Escrow bank
Mashreq Bank Psc
DLD project no.
3186

Latest site photos

April 14, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. April 14, 2026

    6 months after the previous inspection

    +13.8%18.5%
  2. October 7, 2025

    14 months after the previous inspection

    +4.7%4.7%
  3. August 6, 2024

    First inspection

    0%

Thinking about The Autograph S Series at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3186), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat