The Atria by Deyaar at Business Bay

Construction progress

The Atria by Deyaar at Business Bay construction updates

Business Bay · Deyaar Development (P.J.S.C)

CompletedLast site inspection December 31, 2018 · 8 years ago
100%complete

DLD first inspected the site on Oct 1, 2015 at 22% complete, and recorded it as finished after 10 inspections, the last on Dec 31, 2018.

First inspection · 22%Latest · 100%
Construction started
February 20, 2014
Completion date registered with DLD
April 30, 2018
Site inspections
10
Units
577
Buildings
2
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
1483

Latest site photos

December 31, 2018

Progress over time

Progress over time
0%25%50%75%100%201620172018

Inspection history

  1. December 31, 2018

    3 months after the previous inspection

    +2%100%
  2. September 30, 2018

    6 months after the previous inspection

    +3%98%
  3. March 28, 2018

    3 months after the previous inspection

    +4%95.1%
  4. January 8, 2018

    6 months after the previous inspection

    +17.2%91%
  5. July 20, 2017

    4 months after the previous inspection

    +10.5%73.8%
  6. March 22, 2017

    3 months after the previous inspection

    +8.2%63.3%
  7. December 21, 2016

    4 months after the previous inspection

    +18.1%55.1%
  8. August 9, 2016

    5 months after the previous inspection

    +9%37%
  9. March 21, 2016

    6 months after the previous inspection

    +6%28%
  10. October 1, 2015

    First inspection

    22%

Thinking about The Atria by Deyaar at Business Bay?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 1483), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.