Construction progress
Business Bay · Deyaar Development (P.J.S.C)
DLD first inspected the site on Oct 1, 2015 at 22% complete, and recorded it as finished after 10 inspections, the last on Dec 31, 2018.
December 31, 2018
3 months after the previous inspection
6 months after the previous inspection
3 months after the previous inspection
6 months after the previous inspection
4 months after the previous inspection
3 months after the previous inspection
4 months after the previous inspection
5 months after the previous inspection
6 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 1483), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.