Terrazzo Residences at JVC

Construction progress

Terrazzo Residences at JVC construction updates

JVC · Taraf Development L.L.C

Under constructionLast site inspection July 27, 2026 · 3 months ago
95.2%complete

When DLD first inspected the site on May 24, 2023, it was 0% complete. After 10 inspections it now stands at 95.2%.

That is about 2.5% more of the building completed each month on average.

First inspection · 0%Latest · 95.2%
Construction started
November 1, 2023
Completion date registered with DLD
May 20, 2026
Site inspections
10
Units
211
Buildings
3
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2675

Latest site photos

July 27, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. July 27, 2026

    4 months after the previous inspection

    +10.7%95.2%
  2. April 6, 2026

    4 months after the previous inspection

    +16.1%84.5%
  3. December 3, 2025

    2 months after the previous inspection

    +9.1%68.4%
  4. September 24, 2025

    3 months after the previous inspection

    +20.3%59.3%
  5. June 17, 2025

    3 months after the previous inspection

    +18.9%39%
  6. March 12, 2025

    4 months after the previous inspection

    +13.3%20.1%
  7. November 4, 2024

    4 months after the previous inspection

    +6.7%6.8%
  8. July 3, 2024

    7 months after the previous inspection

    0%
  9. December 13, 2023

    7 months after the previous inspection

    +0%0%
  10. May 24, 2023

    First inspection

    0%

Thinking about Terrazzo Residences at JVC?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2675), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.