Terra Heights by Emaar at Emaar South

Construction progress

Terra Heights by Emaar at Emaar South construction updates

Emaar South · Dwtc Emaar L.L.C

Under constructionLast site inspection July 31, 2026 · 3 months ago
9.1%complete

When DLD first inspected the site on Nov 6, 2024, it was 0% complete. After 5 inspections it now stands at 9.1%.

That is about 0.4% more of the building completed each month on average.

First inspection · 0%Latest · 9.1%
Construction started
April 10, 2025
Completion date registered with DLD
March 31, 2029
Site inspections
5
Units
1,004
Buildings
4
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3381

Latest site photos

July 31, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. July 31, 2026

    3 months after the previous inspection

    +5.8%9.1%
  2. April 21, 2026

    7 months after the previous inspection

    +2.3%3.4%
  3. September 7, 2025

    4 months after the previous inspection

    +1.1%1.1%
  4. May 23, 2025

    7 months after the previous inspection

    0%
  5. November 6, 2024

    First inspection

    0%

Thinking about Terra Heights by Emaar at Emaar South?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3381), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.