Symphony by Nshama at Town Square Dubai

Construction progress

Symphony by Nshama at Town Square Dubai construction updates

Town Square · Nshama Properties Owned By Nshmi Development One Person Company L.L.C

Under constructionLast site inspection April 30, 2026 · 6 months ago
73.2%complete

When DLD first inspected the site on Sep 19, 2023, it was 0% complete. After 8 inspections it now stands at 73.2%.

That is about 2.3% more of the building completed each month on average.

First inspection · 0%Latest · 73.2%
Construction started
February 5, 2024
Site inspections
8
Units
398
Buildings
2
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
2786

Latest site photos

April 30, 2026

Progress over time

Progress over time
0%25%50%75%100%202420252026

Inspection history

  1. April 30, 2026

    4 months after the previous inspection

    +16.3%73.2%
  2. December 15, 2025

    5 months after the previous inspection

    +21.3%56.9%
  3. July 3, 2025

    4 months after the previous inspection

    +19.7%35.6%
  4. February 24, 2025

    2 months after the previous inspection

    +8.5%15.9%
  5. December 12, 2024

    0 days after the previous inspection

    7.4%
  6. December 12, 2024

    0 days after the previous inspection

    7.4%
  7. December 12, 2024

    15 months after the previous inspection

    +7.4%7.4%
  8. September 19, 2023

    First inspection

    0%

Thinking about Symphony by Nshama at Town Square Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2786), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.

WhatsAppCallLive Chat