Symbolic Alpha at Liwan Dubailand

Construction progress

Symbolic Alpha at Liwan Dubailand construction updates

Dubailand · Symbolic Real Estate Development L.L.C

CompletedLast site inspection February 28, 2025 · 2 years ago
100%complete

DLD first inspected the site on Jun 12, 2023 at 0% complete, and recorded it as finished after 5 inspections, the last on Feb 28, 2025.

First inspection · 0%Latest · 100%
Construction started
August 31, 2023
Completion date registered with DLD
February 24, 2025
Site inspections
5
Units
97
Escrow bank
Emirates Nbd Bank (P.J.S.C)
DLD project no.
2668

Latest site photos

February 28, 2025

Progress over time

Progress over time
0%25%50%75%100%20242025

Inspection history

  1. February 28, 2025

    4 months after the previous inspection

    +26.9%100%
  2. October 23, 2024

    2 months after the previous inspection

    +17.3%73.1%
  3. August 26, 2024

    4 months after the previous inspection

    +24.5%55.9%
  4. May 3, 2024

    11 months after the previous inspection

    +31.4%31.4%
  5. June 12, 2023

    First inspection

    0%

Thinking about Symbolic Alpha at Liwan Dubailand?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2668), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.