Sunlight Homes at Warsan 4, Dubai

Construction progress

Sunlight Homes at Warsan 4, Dubai construction updates

Al Warsan Dubai · Sunn And Sand Developers

Under constructionLast site inspection June 1, 2026 · 5 months ago
22.1%complete

When DLD first inspected the site on Aug 5, 2025, it was 0% complete. After 2 inspections it now stands at 22.1%.

That is about 2.2% more of the building completed each month on average.

First inspection · 0%Latest · 22.1%
Construction started
June 30, 2025
Completion date registered with DLD
September 30, 2027
Site inspections
2
Units
30
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3827

Latest site photos

June 1, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. June 1, 2026

    10 months after the previous inspection

    +22.1%22.1%
  2. August 5, 2025

    First inspection

    0%

Thinking about Sunlight Homes at Warsan 4, Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3827), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.