Construction progress
Al Warsan Dubai · Sunn And Sand Developers
When DLD first inspected the site on Aug 5, 2025, it was 0% complete. After 2 inspections it now stands at 22.1%.
That is about 2.2% more of the building completed each month on average.
June 1, 2026
10 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3827), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.