Stamn One at Jumeirah Garden City

Construction progress

Stamn One at Jumeirah Garden City construction updates

Al Satwa Dubai · Stamn Real Estate Development L.L.C

Under constructionLast site inspection August 25, 2026 · 2 months ago
42.1%complete

When DLD first inspected the site on Oct 22, 2024, it was 0% complete. After 6 inspections it now stands at 42.1%.

That is about 1.9% more of the building completed each month on average.

First inspection · 0%Latest · 42.1%
Construction started
February 15, 2025
Completion date registered with DLD
October 15, 2026
Site inspections
6
Units
77
Escrow bank
First Abu Dhabi Bank P.J.S.C.
DLD project no.
3243

Latest site photos

August 25, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 25, 2026

    2 months after the previous inspection

    +10.8%42.1%
  2. June 11, 2026

    4 months after the previous inspection

    +14.2%31.3%
  3. February 24, 2026

    3 months after the previous inspection

    +12.3%17.1%
  4. November 20, 2025

    0 days after the previous inspection

    4.8%
  5. November 20, 2025

    13 months after the previous inspection

    +4.8%4.8%
  6. October 22, 2024

    First inspection

    0%

Thinking about Stamn One at Jumeirah Garden City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3243), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.