Construction progress
Al Satwa Dubai · Stamn Real Estate Development L.L.C
When DLD first inspected the site on Oct 22, 2024, it was 0% complete. After 6 inspections it now stands at 42.1%.
That is about 1.9% more of the building completed each month on average.
August 25, 2026
2 months after the previous inspection
4 months after the previous inspection
3 months after the previous inspection
0 days after the previous inspection
13 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 3243), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.