SquareX Residence at JVC Dubai

Construction progress

SquareX Residence at JVC Dubai construction updates

JVC · Tasmeer Indigo Real Estate Development L.L.C

Under constructionLast site inspection September 1, 2026 · 2 months ago
58%complete

When DLD first inspected the site on Jan 18, 2024, it was 0% complete. After 7 inspections it now stands at 58%.

That is about 1.8% more of the building completed each month on average.

First inspection · 0%Latest · 58%
Construction started
April 5, 2024
Site inspections
7
Units
175
Escrow bank
United Bank Limited (Management Office)
DLD project no.
2919

Latest site photos

September 1, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. September 1, 2026

    2 months after the previous inspection

    +1.8%58%
  2. July 8, 2026

    5 months after the previous inspection

    +15.7%56.1%
  3. February 13, 2026

    4 months after the previous inspection

    +17.4%40.4%
  4. October 22, 2025

    2 months after the previous inspection

    +6.6%23.1%
  5. August 19, 2025

    7 months after the previous inspection

    +10.9%16.4%
  6. January 3, 2025

    12 months after the previous inspection

    +5.5%5.5%
  7. January 18, 2024

    First inspection

    0%

Thinking about SquareX Residence at JVC Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2919), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.