Construction progress
Sports City Dubai · Danube Properties Development L.L.C
When DLD first inspected the site on Nov 14, 2023, it was 0% complete. After 11 inspections it now stands at 80.2%.
That is about 2.3% more of the building completed each month on average.
October 8, 2026
31 days after the previous inspection
4 months after the previous inspection
2 months after the previous inspection
20 days after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
3 months after the previous inspection
5 months after the previous inspection
9 months after the previous inspection
5 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2845), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.