South Living by Dubai South

Construction progress

South Living by Dubai South construction updates

Dubai South · Dubai South Properties Dwc Llc

Under constructionLast site inspection July 28, 2026 · 3 months ago
88.8%complete

When DLD first inspected the site on Jan 28, 2025, it was 4.8% complete. After 4 inspections it now stands at 88.8%.

That is about 4.7% more of the building completed each month on average.

First inspection · 4.8%Latest · 88.8%
Construction started
January 5, 2018
Completion date registered with DLD
February 5, 2020
Site inspections
4
Units
209
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
1946

Latest site photos

July 28, 2026

Progress over time

Progress over time
0%25%50%75%100%2026

Inspection history

  1. July 28, 2026

    5 months after the previous inspection

    +23.6%88.8%
  2. February 12, 2026

    6 months after the previous inspection

    +35.4%65.2%
  3. August 20, 2025

    7 months after the previous inspection

    +25%29.8%
  4. January 28, 2025

    First inspection

    4.8%

Thinking about South Living by Dubai South?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 1946), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.