Construction progress
JVT · Condor Concept 7 View Real Estate Development L.L.C
When DLD first inspected the site on Jan 24, 2024, it was 0% complete. After 8 inspections it now stands at 74.4%.
That is about 2.3% more of the building completed each month on average.
October 20, 2026
2 months after the previous inspection
2 months after the previous inspection
2 months after the previous inspection
4 months after the previous inspection
6 months after the previous inspection
5 months after the previous inspection
12 months after the previous inspection
First inspection
Ask us about available units, prices and the payment plan. We reply on WhatsApp.
Source: Dubai Land Department project status and site inspection records (project no. 2923), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.