Sonate Residences at JVT

Construction progress

Sonate Residences at JVT construction updates

JVT · Condor Concept 7 View Real Estate Development L.L.C

Under constructionLast site inspection October 20, 2026 · 18 days ago
74.4%complete

When DLD first inspected the site on Jan 24, 2024, it was 0% complete. After 8 inspections it now stands at 74.4%.

That is about 2.3% more of the building completed each month on average.

First inspection · 0%Latest · 74.4%
Construction started
March 6, 2024
Site inspections
8
Units
215
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
2923

Latest site photos

October 20, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 20, 2026

    2 months after the previous inspection

    +8.4%74.4%
  2. September 4, 2026

    2 months after the previous inspection

    +8.1%66%
  3. July 10, 2026

    2 months after the previous inspection

    +16.6%57.9%
  4. April 27, 2026

    4 months after the previous inspection

    +10.6%41.3%
  5. December 19, 2025

    6 months after the previous inspection

    +13.9%30.7%
  6. June 19, 2025

    5 months after the previous inspection

    +4%16.8%
  7. January 14, 2025

    12 months after the previous inspection

    +12.8%12.8%
  8. January 24, 2024

    First inspection

    0%

Thinking about Sonate Residences at JVT?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 2923), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.