Sobha Solis at Dubai Motor City

Construction progress

Sobha Solis at Dubai Motor City construction updates

Motor City Dubai · Sobha L.L.C

Under constructionLast site inspection October 22, 2026 · 16 days ago
17.9%complete

When DLD first inspected the site on Oct 22, 2024, it was 0% complete. After 5 inspections it now stands at 17.9%.

That is about 0.7% more of the building completed each month on average.

First inspection · 0%Latest · 17.9%
Construction started
October 3, 2024
Completion date registered with DLD
December 31, 2028
Site inspections
5
Units
2,351
Buildings
6
Escrow bank
Abu Dhabi Commercial Bank
DLD project no.
3334

Latest site photos

October 22, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. October 22, 2026

    6 months after the previous inspection

    +4.7%17.9%
  2. May 5, 2026

    3 months after the previous inspection

    +3.9%13.2%
  3. January 29, 2026

    4 months after the previous inspection

    +5.7%9.4%
  4. September 29, 2025

    11 months after the previous inspection

    +3.7%3.7%
  5. October 22, 2024

    First inspection

    0%

Thinking about Sobha Solis at Dubai Motor City?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3334), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.