Sobha Orbis at Motor City Dubai

Construction progress

Sobha Orbis at Motor City Dubai construction updates

Motor City Dubai · Sobha L.L.C

Under constructionLast site inspection August 13, 2026 · 3 months ago
18.2%complete

When DLD first inspected the site on May 14, 2024, it was 0% complete. After 4 inspections it now stands at 18.2%.

That is about 0.7% more of the building completed each month on average.

First inspection · 0%Latest · 18.2%
Construction started
June 1, 2024
Completion date registered with DLD
December 31, 2028
Site inspections
4
Units
3,002
Buildings
8
Escrow bank
Dubai Islamic Bank (Public Joint Stock Company)
DLD project no.
3070

Latest site photos

August 13, 2026

Progress over time

Progress over time
0%25%50%75%100%20252026

Inspection history

  1. August 13, 2026

    5 months after the previous inspection

    +6.5%18.2%
  2. March 25, 2026

    9 months after the previous inspection

    +5.3%11.7%
  3. July 4, 2025

    14 months after the previous inspection

    +6.4%6.4%
  4. May 14, 2024

    First inspection

    0%

Thinking about Sobha Orbis at Motor City Dubai?

Ask us about available units, prices and the payment plan. We reply on WhatsApp.

Source: Dubai Land Department project status and site inspection records (project no. 3070), checked November 6, 2026. Completion percentages are DLD's measurements of work on site, not the developer's handover commitment. Photos were taken by DLD inspectors.